Our factory is a purpose-built building of approximately 10,000 m².

A well adapted factory

Our factory and head office have been expanded in several stages. The original premises date back to the 1960s. The production area has been increased through expansions in 2006 and 2017. Warehouse tents have been added. The office space has been expanded during the expansions in 1992 and 2016.

The factory building, which is currently 200 meters long and 50 meters wide and covers an area of ​​approximately 10,000 m², provides good conditions for a good production flow. No unnecessary transport between buildings and no intersecting material flows. Just one long and easily understandable process. Material in one end, finished windows out the other.

Another factory expansion is underway. During the second half of 2026, we plan to have approximately 13,000 m² of production space in order to increase capacity and manufacture even more windows than today.

LEIAB 2007

LEIAB 2025

LEIAB 2019

  • Factory Expansion 2025

    Film from October 2025

2025–2026: New factory expansion

In 2025, we have started a new expansion of the factory with approximately 3,800 m². Sooner or later the construction industry will boom again and then we will be ready to manufacture even more windows than today.

June 2025: Land preparation begins to create a new location for the storage tents.

The new factory premises are planned to be ready for occupancy in August 2026.

29 September 2025: The roof trusses have been put in place and the first wall elements have been installed.

August 2025: The image shows that the expansion consists of both production space and warehouse space and a new road. The warehouse tents have now been moved and half of the new road has been paved. Ground preparation and burying of plinths is underway.

8 October 2025: Soon all the wall elements are in place.

15 September 2025: The installation of columns is underway and the first roof trusses have also arrived in place.

 

16 October 2025: Now all the wall elements are in place and the pillars for the screen roof will soon be installed.

2017–2019: Last factory expansion

In 2017, we extended the factory by approximately 2,200 m². Below are images showing the progress of the construction.

March 2017: Our old cold storage is being demolished to make room for the new production facility.

It didn’t take many days to demolish the cold storage. The area is now clear and we’re waiting for groundwork to begin so the frame can be built.

April 2017: You can now start to see where the columns for the new factory will be placed.

A few days later. Looks like we’re staying on schedule.

May 2017: The columns are now in place, and it’s almost time for the roof trusses.

Almost all root trusses are placed, and a part of the wall has also been started at the far end.

June 2017: The walls and most of the roof are in place. We hope that the windows are delivered on time…

July 2017: The whole roof is placed and the floor has been cast. Electric and lighting work has begun, followed by ventilation – and then it’s time for new machines.

August 2017: The exterior is nearly finished, and the final inspection is coming up soon.

December 2017: The factory expansion is complete, and a new paint shop for wooden components has been installed.

December 2018: The paint line is operational, and a new wood line is being installed.

Reference

Brf Uppsalahus 9 , Uppsala